How Progressive billing ( not Milestone Billing.) is handled in SAP.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

answered

hueychin_liew
Active Participant
0 Kudos

Hi JJSingh76,

Please review note 830097 & let us know if the information is sufficient for your understanding for milestone billing?

Otherwise, please let us know what in specific info is missing.

Thank you.

Best regards,

Huey Chin

Former Member
0 Kudos

The requirement is billing is done based on the % of completion at the end of each month. For example if the project is 12 months & in Jan 15% of project completed then invoice for 15% of the contract value is raised. Again in Feb if 20% is completed then Invoice for 20% of the contract value is raised.

How invoice can be generated in SAP in this scenario?

Former Member
0 Kudos

hi,

i am also having the same problem. does anybody has a solution how to map it into SAP?

Mrinal_K_Roy
Active Contributor
0 Kudos

Hi,

One way of doing it will be to

Create 5 milestone and 5 line items in billing plan (in case of 20% billing) . Billing block in each line item can be removed by confirming each milestone.

With regards,