SNP Heuristic Planning

Former Member
0 Kudos

Hi SAP Gurus:

I have client requirement where client wants to create planned order w/o considering any receipt element in the system.

Eg: For Month of June forecast is 1000 unit and stock in inventory is 300 so currently planned order of 700 is getting created.But customer need that planned order of 1000 unit should be generated w/o considering stock of 300 unit.How can we get it in SNP heuristic.Can we run gross planning in SNP heuristic ?

Regards

Ashish Gupta

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Ashish,

Try ignoring the ATP categories which you don't want to include during planning and then carry out the planning.

Regards,

R. Senthil Mareeswaran.

Former Member
0 Kudos

hi!!!

place some custom created ATD reciept element say "ZS" in the Stock category group of location master which does not ve a single stock.. this should help you.

Regards

Vaibhav Sareen

Former Member
0 Kudos

do you want this for all material or for selected materials?

if for selected materials then you can switch of stock model of those materials.

Former Member
0 Kudos

stock model, means the integration model of stock.