Hello,

My problem is that when I create a project and I assign WBS, for the transaction CJ20N. Loads the budget for the Tr. CJ30 and I liberate it for the CJ32. The status of the WBS is placed: REL, AVAC, BUDG, SETC. The AVAC is activated. Later this control of availability is deactivated using the CJBW, it eliminates AVAC's check. The active thing again Tr. CJBV. Though the system says that the AVAC is activated, it is not reflected in the status of the WBS and AVAC's box remains unmarked. And if I try to do a post bigger than what I have in the budget it to happen without noticing. My question since as can I return activate the control of availability?. Also I tried with CJEN and nothing

I am grateful for them enormously if they help me with this.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

You have to reconstruct Availability control after evry operation like activation or deactivation. It means run CJBN after every CJBW or CJBV. Hope this resolves your issue.

Thanks

Raghu

Former Member
0 Kudos

Hi,

try CJBn to reconstruct AVAC

regards!

anishpv
Participant
0 Kudos

[]

Mrinal_K_Roy
Active Contributor
0 Kudos

Hi Mariela,

Your case seems to correspons to the case described in 33091 . You may try trhe steps stated in note 16710.

Regrads,,

Mrinal

Former Member
0 Kudos

Hello,

Checked everything what says the note and in my systema is ok.

Some another suggestion?