Hi All
what is the functions of the project version and selection version and difference between the same.
Thanks
S.Murali
Hi,
Refer below sap help link for function and use of project version & selection version.
project version
http://help.sap.com/erp2005_ehp_04/helpdata/EN/d8/1fe8344d1d166be10000009b38f83b/frameset.htm
selection version
http://help.sap.com/saphelp_erp60_sp/helpdata/en/ee/41f41846ee11d189470000e829fbbd/content.htm
Regards,
Sandeep
Edited by: Sandeep Theurkar on May 23, 2009 1:29 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
project version is just a snap shot at a perticular point of time which stores all project related details in that version but selection version is to save the report in information system for a specific time period sothat you can check the report with the selection version. its like retriving data through selection profile from database.
Hope this clear your doubt.
regards,
Hari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.