easy cost planning

Former Member
0 Kudos

Cost planning using easy cost planning not shown in CJ30 under Planned total, so that they can copied for budget. Why so?

Accepted Solutions (1)

Accepted Solutions (1)

stheurkar
Active Contributor
0 Kudos

Hi,

ECP mainly used for only cost planning purposes & you can make best use of this tool in the following processes of PS.

● Project processing concentrating on cost controlling

● Preliminary costing for complex projects

You can find more details referring below link on ECP in Project System.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/9d/8e88387f599020e10000009b38f8cf/content.htm

In following condition system is transferring values from cost planning as budget.For the same refer below link.

Also this link will tell you how Plan Total consists, which reflects in CJ30 as Planned Total.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/fa/74a937016fd743e10000009b38f842/content.htm

I hope this will clear you.

Regards,

Sandeep

Edited by: Sandeep Theurkar on May 23, 2009 1:07 PM

0 Kudos

hello expert.. I have one issue in ECP.. My planned cost for few cost elements are not reflecting in CJ30 as a planned cost for version. I checked and found that the cost planned on primary cost elements are not reflecting under CJ30. Could you please help me.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Check which CO version you are using for ECP.Transfer planned costs to budget by IMCCP3.

Muzamil

stheurkar
Active Contributor
0 Kudos

Hi,

Use tcode IMCCP3 to copy planned cost to budget

Sandeep

Former Member
0 Kudos

Thx.....

But why it does not show up in CJ30..any specific reason??

anishpv
Participant
0 Kudos

Hi,

Check following things 1.CO version defined for ECP 2.Costing variant PS06 in Plan Profile

Rgds

pv