Cost planning using easy cost planning not shown in CJ30 under Planned total, so that they can copied for budget. Why so?
Hi,
ECP mainly used for only cost planning purposes & you can make best use of this tool in the following processes of PS.
● Project processing concentrating on cost controlling
● Preliminary costing for complex projects
You can find more details referring below link on ECP in Project System.
http://help.sap.com/saphelp_erp60_sp/helpdata/en/9d/8e88387f599020e10000009b38f8cf/content.htm
In following condition system is transferring values from cost planning as budget.For the same refer below link.
Also this link will tell you how Plan Total consists, which reflects in CJ30 as Planned Total.
http://help.sap.com/saphelp_erp60_sp/helpdata/en/fa/74a937016fd743e10000009b38f842/content.htm
I hope this will clear you.
Regards,
Sandeep
Edited by: Sandeep Theurkar on May 23, 2009 1:07 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check which CO version you are using for ECP.Transfer planned costs to budget by IMCCP3.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use tcode IMCCP3 to copy planned cost to budget
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.