Please confirm that by making the status CLSD , what would happen to the project if it has cost in Profit&Loss and not settled. In the projects we plan to close there is no settlement rule defined
Hi,
If you wanted to close project without settlement, refer below link which will give some input to you.
https://forums.sdn.sap.com/click.jspa?searchID=26494928&messageID=4738550
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If settlement profile it meant for settlement then you cant close the project.If settlement profile is not meant for settlement then you can close the project.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
CLSD means means you cant post commitment & actual both.
and for settlement, it depends on what settings you have maintained in settlement profile; if settlement is mandatory than the project will not close unless settled or if settlement is set to not required then project will close as it is with no costs or revenues settled.
regards!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
TECO means u cant post commitment but actuals allows.
CLSD means u cant post comitment & actual both.
u should settle all actuals before u clsoe the project.
Reg,
sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
by closing means one cannot post commitments as well as actuals to the project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.