Message "No Line Items Selected"

Former Member
0 Kudos

Hi friends,

I am getting a message "No Line Items were selected" while executing CJI4.

Or even when in the transaction CJ40/CJ41, I am going thru ....Extra>Line Items.......

I have even implemented a note but still the same message is coming.

I couldnot figure out what "Line Items" the system is asking for.

Pl. help me out.

--

Abhra Bose

9930459159

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi,

what is your error in CJ40?

maybe you have not maintained the wbs elements as planning elements.. to do this you need to tick the indicator in proj builder, or change the planning profile..

rgds.

Former Member
0 Kudos

HI Ramesh,

WBS element is already marked as a Planning element & planning is also been done in CJ40 in version 1.

But if you follow the link as stated the report is not getting generated.

I have already used the User Status of Write Plan Line Item.

rgds,

Abhra

Former Member
0 Kudos

Refer to this note if applicable to your SAP pack: Note 1130282 - CJ40/CJ41: Plan line items not displayed.

1. Check planning profile assigned to your project definition.

2. Check Primary C.Element Grouping defined in the profile for Hierarchial Cost Planning. (if not defined use T.code CJR2 to build WBS detailed planning)

3. Check Number Range assignement for Detailed Planning for the controlling area and transactions assignment to intervals.

4. User Status maintained for WBS elements must allow "write plan items" business transaction.

Hope it all helps.

NChakoo

Edited by: NAKUL CHAKOO on May 27, 2009 9:56 PM