on 05-22-2009 8:11 AM
Hi friends,
I am getting a message "No Line Items were selected" while executing CJI4.
Or even when in the transaction CJ40/CJ41, I am going thru ....Extra>Line Items.......
I have even implemented a note but still the same message is coming.
I couldnot figure out what "Line Items" the system is asking for.
Pl. help me out.
--
Abhra Bose
9930459159
hi,
what is your error in CJ40?
maybe you have not maintained the wbs elements as planning elements.. to do this you need to tick the indicator in proj builder, or change the planning profile..
rgds.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Refer to this note if applicable to your SAP pack: Note 1130282 - CJ40/CJ41: Plan line items not displayed.
1. Check planning profile assigned to your project definition.
2. Check Primary C.Element Grouping defined in the profile for Hierarchial Cost Planning. (if not defined use T.code CJR2 to build WBS detailed planning)
3. Check Number Range assignement for Detailed Planning for the controlling area and transactions assignment to intervals.
4. User Status maintained for WBS elements must allow "write plan items" business transaction.
Hope it all helps.
NChakoo
Edited by: NAKUL CHAKOO on May 27, 2009 9:56 PM