Dear All

I have one business scnerio as follows

I have Created one user status for WBS as Z-Ustat

This user status contain Following

each project is going to approved by chairmen(proposed by plant head)

!)proposed for approval

2) approved For execution

3)droped By business cell

4) carry forward for Next year

in my project First level WBS element is always ONE i stricted in Project profile

for above user status i linked in Project profile. now my problem is

when ever i'm proposing the WBS i need to propose each WBS element(need to change user status in every element) the same thing happening for approval

i required to Collective approval

in the project first level WBS element always ONE.if i'm proposing first level WBS element all the lower level wbs element should change the use status

pl suggest me the Solution

Accepted Solutions (1)

Accepted Solutions (1)

stheurkar
Active Contributor
0 Kudos

Hi,

You can update user statuses from level 1 to all lower levels. by using following menu path.

enter CJ20N transaction.

see on left side of screen, click on Project Defn. then,

see on right side of screen,click on WBS Element Overview buttuon ( Yellow Triangle Buttuon)

select all WBS Element (ctrlshiftf3)

Edit > Status > User Status > Set > here you will get list of User Statuses, double click on reqd. user status continue. This will update selected user status from level 1 to all lower level WBS Elements.

save.

Regards,

Sandeep

Edited by: Sandeep Theurkar on May 22, 2009 10:50 AM

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear rajesh h,

just open project on CJ20N & expand all, select the top levl WBS or Proj definition.

Go to Menue EDIT >Status>User Status-->Set ans Pass on then apper the available user status, select the one u need to set & save the project.

hope this will help u.

Reg,