Material cost problem?

Dear all:

For the one finished goods, if all most the material was client provided and a few material was to buy it by ourself. If material was client to provided that it's not calculating the cost, if material was ourself to buy it that need to calculate cost.

For this situation, how can to meet this requirement?

Notes: for this situation, provider is parent company and from the subsidiary manufacture the products. In the system include two companys.

Edited by: Nicole Chen on May 22, 2009 4:41 AM