tab " delivery" in po .use of reminder field

Sir,

In a po there is a delivery tab where we set reminders 1,2,3

how is this functioning with delivery date as well as how are the reminders send to vendors

ply explain

regards

amey

Former Member
Former Member replied

Hi Amey ,

The standard o/p type used for dunning is MAHN.

If you have already done customising for o/p type NEU in case of PO , the same customising applies to MAHN , only the o/p Form may Change.

Maintain the condition records in MN04 and monitor the same in Transaction ME91F.

Regards

Ramesh Ch