on 05-20-2009 3:48 PM
Hi,
When picking materials, the system allows you to pick and pack even if the material batches are different from the Sales Order batch.
My question, how do I get the SAP system to stop the picker if they are picking the incorrect batch? Is there a setting in SPRO?
Thanks! Any help would be great.
are you want to say that the people are changing the proposed (from sales order) batch number in the delivery manually and enter a different one.
Have you talked to the people why they are doing this?