DSEX status in PRocess orderq

Hi,

Can some one have information on how status DSEX is set on process orders at operation level ?

We use APO also for planning.

Regards

BVN

Former Member
Former Member replied

Hi,

DSEX - Date set by external system

As you said, you are using APO that may be the reason for this Status..

Best Regards,

Siva