on 05-20-2009 12:54 PM
hi expert,
There are values for cost element 400406 that are not assigned to any line ID
Message no. KJ161
Diagnosis
Not all values for the cost element are assigned to a line ID.
Procedure
Assign the cost element to a line ID. If you don't want to include the cost element in results analysis, assign it to a line ID of category N.
You can access a detailed list of unassigned cost elements as follows: Start results analysis in the individual processing mode (transaction KKA1, KKA2, or KKA3). Select the field Full log. Execute the function. On the next screen, choose Logs -> Parameter List in the menu. A list is generated. The unassigned values are shown at the end of the list.
If cost element "+++++++++" was shown in the message, this is because in the assignment of costs and revenues to line IDs, you have not used a cost element other than the full masking "+++++++++". In this case a presummarization eliminates the information on the cost element.
thanks in advance.
solved myself.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.