Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

ProcessChain Enhancement..

Hi,

We hav the data 2003, 2004 and 2005

(Full Update) packages in process chain.

Now our requirement is to delete the 2003 data from the proc chain and insert new pack i.e. 2006 data

Now I want to delete the 2003 data from the cube and change date selection in the infopack to 2006

So, here we need not to insert new infpack in process chain. Right? Or we need to delete the entire infopack(2003 ) and insert 2006 new infopack in processchain ? which one is the best solution …..

We just need to change the date selection to 2006 from 2003 infopack…

After doing theses changes in Dev and how to transport these changes to Prod ?

Can anyone suggest me on this…

Thanx in Adv…

SSR

Not what you were looking for? View more on this topic or Ask a question