Hi experts,
Our client expecting mail two times i.e., when expenditure reaches 50% and 90% of the budget of the WBSE. But standard SAP is providing mail to responsible person is only once. Is there any way to overcome this problem.
Hi,
If you want a mail to be trigger when expediture reaches upto 50% & 90% of the budget.Try below settings.
Co.Ar. Prof. Text Tr.Grp. Act. Usage
1000 BUDPRF Budget Profile 06 2 50%
1000 BUDPRF Budget Profile ++ 2 90%
In standard sap ps, for one activity group you can set one action, you can try for this also, then system will give error message as "Target key must be different from source key"
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think no.You can check development for this.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Did u tried by putting to lines in tolerance limit. one with 50 % usage n mail to responsible person n for the same budget profile with 90% n again with message type 2 .
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.