on 05-20-2009 5:57 AM
can anybody explain me how to transfer bom component in network activities ? pls
Hi,
You either use CN33 or directly explode BOM In project builder.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1Please check example in IDES for Material T-20000 for reference points.Attach the Parent material to Activity and then run CN33 system will transfer the BOM to your activities.
2.But if you want to explode BOM in CJ20N then attach Parent material to activity then click activity go to edit-component-Explode BOM.
Muzamil
thanks to all
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please refer the following link for a very detailed process provided by SAP under Material> Bill of Material Transfer > Assigning BOM items using Bill of Materials transfer.
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm]
As there are different scenarios provided for a BOM transfer, it is imperative that this needs to be explored as per the requirement.
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
First of all u have to define reference point for the activit y in the Assignment where u want to assign the BOM.This can be a alphanumeric number. In CJ20N itself u can define reference pt Just by pressing F4 in reference pt filed. Mainatan same ref pt in BOM. treansfer this BOM to activity thru CN33.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.