bom component transfer to project builder

Former Member
0 Kudos

can anybody explain me how to transfer bom component in network activities ? pls

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You either use CN33 or directly explode BOM In project builder.

Muzamil

Former Member
0 Kudos

can you explain me the procedure ? pls

Former Member
0 Kudos

Hi,

1Please check example in IDES for Material T-20000 for reference points.Attach the Parent material to Activity and then run CN33 system will transfer the BOM to your activities.

2.But if you want to explode BOM in CJ20N then attach Parent material to activity then click activity go to edit-component-Explode BOM.

Muzamil

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks to all

Former Member
0 Kudos

Please refer the following link for a very detailed process provided by SAP under Material> Bill of Material Transfer > Assigning BOM items using Bill of Materials transfer.

[http://help.sap.com/saphelp_erp60_sp/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm]

As there are different scenarios provided for a BOM transfer, it is imperative that this needs to be explored as per the requirement.

Venu

Former Member
0 Kudos

Hi ,

First of all u have to define reference point for the activit y in the Assignment where u want to assign the BOM.This can be a alphanumeric number. In CJ20N itself u can define reference pt Just by pressing F4 in reference pt filed. Mainatan same ref pt in BOM. treansfer this BOM to activity thru CN33.

Rgds

Former Member
0 Kudos

any tcode for the same to create ref. point