on 05-19-2009 11:09 PM
What would you say is the amount of time it would take to implement CUP, in the simplest way possible? In other words, barring unforeseen circumstances, and with the simplest workflows, how long would it take?
Thanks a lot ...
Santosh
Hi Santosh
I hope you have RAR installed in your system.
To implement CUP you can follow the plan below,
1. Compliant User Provisioning Implementation 14 days
2 Complete AE Pre-Implementation Checklist 1 day
3. Deploy and install AE on NW 1 day
4. Perform AE post -installation configuration and connectivity 1 day
5. Perform AE issue resolution 1 day
6. Discussion & Configuration of Test workflows 7 days
7. Run end to end request scenario testing for each workflow path 3 days
It is upto your project resource allocation and working hours to minimise the task ASAP.
Regards,
Sudip.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Santosh,
You can get CUP working in a couple of days with the simpest workflow. One main dependency would be the number of systems that you want to connect to and the fluency you have over the configurations.
But it should not take much time
Harleen
SAP GRC RIG
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Santosh,
If you want to use CUP in the simplest way with very simple workflows and no custom fields, it should take you around 2-3 weeks.
Regards,
Alpesh