on 05-19-2009 12:19 PM
Dear Experts,
wt is the difference b/w checking avilability with RLT and with out RLT?
How RLT is controlling availability check in sale process?
Regards
Ishikesh
Ishikesh,
Availability check without RLT is like processing the Avail;ability manually, it means If the stock is available system will confirm the availability. Otherwise, you need to reconfirm the order once the stock is updated. You can do this using rescheduling or back order processing.
If availability with RLT is there you have to make sure that one of the following three fields in the material master:
is maintained.
GR (goods receipt) processing time (Purchasing view)
Planned delivery time (MRP I view)
GR processing time (MRP II view)
For more details about Availability and RLT
http://www.saptechies.com/configuring-availability-check/
Thanks,
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In availability check control parameters in OVZ9
Case 1 if the Check without RLT time is not ticked
The means the system is checking with RLT time
RLT time is maintained in MRP 2 view of MMR
If you mention 2 days or 3 days then while creating sales order system will propose delivery is possible only after 2 or 3 days
If RLT is blank there in MMR ,then system assumes at the end of zero days the stocks are available (actually stocks are not there) hence confirms schedule lines in sales order and will create delivery and allow picking and will HIT you in PGI
The MRP type choose here also plays a major role here
Case 2 if the Check without RLT time is ticked
The system will not look in the MMR at all for the RLT parameter andwill confirm stocks only with other parameters like physical inventory ,incoming PO's, incoming PR's like that
More correct way of doing it
Case 1 with RLT time will confuse you a lot as system can confirm stocks for sales order when there is 0 qty in MMBE
Regards
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ishikesh,
RLT is the time needed before the product is completely available again and is manually entered in MRP3
screen. If it is not maintained, then the system adds the processing time from purchasing, the planned delivery time, and the GR processing time and uses this total for an availability check with RLT.
Use OVZ9 to check availability without RLT. Leave this field blank if you want the system to check the
RLT. This means that the availability check for the requirements is processed within RLT.
Requirements outside RLT are generally available as the system assumes that these materials can be made available within RLT via materials planning. If it is not possible to cover a requirement via inward movements, the end of RLT is the earliest date on which one can confirm the materials.
Dependencies
If you want the system to check RLT, you should make sure that you have entered a
value in at least one of the following three fields in the material master:
GR processing time (Purchasing view)
Planned delivery time (MRP I view)
GR processing time (MRP II view)
Regds,
GShankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.