Special Analysis Scedule

Former Member
0 Kudos

Dear QM Experts.

My user requirements to tests the daily schedule inspection of inprocess inspection, this is a process industry.

Please help me in this issue.

Thanks & Regards,

ufarooq

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Inprocess inspection lot gets generated only after release of the process order so you can track it by searching how many order are going to released daily and once that get released you will get an inspection lots

Please revert back

Thanks

Vinay

Former Member
0 Kudos

Dear joshi

How to incorporate schedule of test/analysis of samples in SAP QM module because most of the analysis/testing in laboratory is performed according to schedule which was predefined.

ufarooq

Former Member
0 Kudos

Dear Expert,

Please suggest me, is it possible through t.code sm36 and if it is possible please tell me step by step.

I will be most thankfull to you,

Thanks & Regards,

ufarooq