on 05-19-2009 3:59 AM
Dear all,
My company have some productions that parent items and component items are the same. But SAP B1 doesn't allow us to do this. This error was thrown when I tried to add this kind of production orders or BOM.
"Component cannot be equal to the production item"
For example, in normal situation, a product "A" have component "B" and "C".
"A" 2 kg = "B" 1 kg + "C" 1 kg
But, sometimes, we have to Blend them some previous batch of "A" like this
"A" 3 kg = "B" 1 kg + "C" 1 kg + "A" 1 kg
and then we got 3 kg of "A" in new batch no.
If B1 cannot have this kind of production orders, Is there any other way to do it.
Thanks
hi,
Create a BOM A1 as parent and A as child.
Create a standard prodn. order for A with childs B,C,A1.
Jeyakanthan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Avtar Singh Saini
B1 doesn't allow to add A as a child item after B and C, if A is a parent item (Both in BOM production order). So, what you've suggested is not possible.
HI Jeyakanthan
The production order type are both standard and special. And I got the same error for both type.
thank you for your reply
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
What is production order type ?
Jeyakanthan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I suggest defining one (or more) item for temporary use to represent the item under production.
-First you can make a (probably special type) production order to produce it from its real child items.
- and finally a special type production order to produce the real item.
(If you use such items one at a time in this process, then the cost calculation will be correct too.)
Hi
System is right same item can not be a parent as well as child in single BOM
So there are two solutions
1. Created new item ,A1 like that make a production BOM for that
2. When u add production order on the base of BOM there you can put the parent item in list of child item of production order .
So best is add the item A in Production order with B and C
Waiting for ur reply
Avtar Singh Saini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For standard recipe create a standard production order based on production BOM where A will be parent item and B, and C will be components.
In situations where parent itself is used in production process, create a special production order where A will be parent along with B,C, and A again as components.
Special production orders are not BOM driven. You are free to add the components as per your requirements.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.