请问MD04里面各种物料有时候会存在以下状况,请高手帮我解释一下分别是什么意思~

Finish date in the past

Stock Fallen Below Safty stock Level

Reschedule In

Reschedule out

Cancel process

Plan process according to schedule

希望高手能帮我解释一下

比如说Plan process according to schedule这个

我把一个原本在firm zone内的schedule line删除掉,然后MD02重新单个物料跑MRP,跑完后在

firm zone之外会产生新的schedule line显示 Plan process according to schedule,

我的理解是这是不是和schedule in 类似, schedule in是原来的采购日期和建议采购日期都在

firm zone内,而Plan process according to schedule是原来的日期在firm zone外,但是建议

采购日期在firm zone内?

请MM 模块高手指点。

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Finish date in the past: 如果现有的purchase order, schedule line或者production order中,其订单的finish data是当天之前的日期,则系统会有异常07提示;

Stock Fallen Below Safty stock Level : 依据描述,就是指在该时间点现有库存已经低于安全库存!

Reschedule In & Reschedule out & Plan process according to schedule:出现此提示时的MRP element,都会伴随一个rescheduling date同时出现,是指现有的element与SAP MRP的运行结果不符,系统建议将日期提前或推延至系统所建议的日期,

Plan process according to schedule:按照系统MRP运行的结果,可能会出现订单的开始日期早于当天,或者由于firm zone和planning time fence存在,系统则建议物料计划员根据SAP运行的结果再做出相应的调整;

Cancel process :出现此提示的MRP element,是指SAP MRP运行的结果认为,此MRP element不是必须的,出于最小库存的控制,系统建议取消此条记录。