Hi Experts,

We have created internal activty in the network at the time of saving it is giving an error.

"Error while calcualting Cost,log is deleted when saving do you want to save?".

When I checked the log through extraslogscost calculation in CJ20N,it is showing following reasons

1) Missing formula in work center

2) Operation 0020/suboperation(or cost comp):activity type not entered.

3) No control record for activity type in version 000/2009 activity planning/qty planning.

could you please help me in this?

Regards,

Abdul Rehman

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please maintain the Work center and Activity type Correctly.Some data is missing in Work center and Activity type.

Regards,

Muzamil

Answers (3)

Answers (3)

Makal
Active Contributor
0 Kudos

In your work center, use "SAP008" formula in the costing tab.

Copy the activity type you have used in the work center (again in costing tab) & use this activity type in your project internal activity. Use the same unit of measure in your project internal activity, that you have defined in the activity type.

Define correct rates in KP26 for your activity type.

It should work now.

Good luck.

Former Member
0 Kudos

HI,

1) In work center , make sure you maintain Formula for Activity type int. processing

key in Costing Tab SAP008.

2)Define Activity Type in KL01

3)Define the prize to activity Type in KP26.

4)assign the activity type to work center in costing tab at Activity type int. processing.

Hope it is useful to you

Thanks

Abhijeet

Former Member
0 Kudos

Hi,

check the following:

1.0 In work center , make sure you maintain Formula key in Costing Tab.

2.0 You enter Activity type in Activity in CJ20N.

3.0 You maintain Activity type/price planning in KP26 for version 000 and fiscal year 2009.

Regards,