Is it possible to calculate RLT (Replenishment Lead time) in material master automatically in SAP? WE are following discrete Mfg. process.
Regards,
Alex
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No, This is not possible. TRLT will be maintained always manually for procurement of entire BOM in header assembly.
You can calculate lead time for an assembly from routing and update the same in material master. But TRLT and lead time is different.
Regards
TAJUDDIN