Hi,
We have recently upgraded our client's system to ECC 6.0 from 4.7.
We are facing the issue that whenever user does the manual scheduling of order using CO02, the order's main header material qty resets automatically to 1 whereas in MD04 I can still see the original qty.
Can anyone let me know that why system is behaving like this?
Regards....
In MM02 ,for that material please check the lot size..I suppose that the Fixed lot size field might be filled with 1. please check and change it. then check in CO02..
karthick