on 05-15-2009 2:43 PM
Hi,
How can I check how many hours have been booked against each maintenance plan.
Many thanks.
hi
Normally working hours will be booked only when the call is generated ,hence you can check in IW38 by specifying the maintenance plan no in the selection field and check the hours booked
Also check in IP19 and IP24
regards
thyagarajan