Total hours booked against a maintenance plan

Former Member
0 Kudos

Hi,

How can I check how many hours have been booked against each maintenance plan.

Many thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi

Normally working hours will be booked only when the call is generated ,hence you can check in IW38 by specifying the maintenance plan no in the selection field and check the hours booked

Also check in IP19 and IP24

regards

thyagarajan

Former Member
0 Kudos

Hi

Many thanks for the answer it was very useful.

I went into IW38 and entered the maintenance plan no. and found all the maintenance orders against it.

Then i went into IW49 and put all the maintenance orders in it and it gave out the actual work booked against each order.