Hi,

I created a means of transport combination which consists of one active unit and a trailer. I can load it by running the opt. profile succesfully.

The problem is, the active means of transport can not be used without the trailer anymore. I can load it manually, but the optimization run does not take it into account. If i choose the resources of that means of transport as the only available resources, i get the error message "Error creating model".

Is this a customising problem?

Thanks in advance or your replies.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Have you checked the detld planning flag in the Transportation lane master data for MOT.

Thanks,

Sanjog

Former Member
0 Kudos

Tibor,

I checked the note, all the corrections have already been installed.

Sanjog,

The detld planning flag is already checked in the master data.

Thank you both but the problem still exists.

Former Member
0 Kudos

Problem solved by the implementation of note 983387.

tibor_nagy
Contributor
0 Kudos

Hi,

please check if note 1111832 could help you.

Regards,