on 05-15-2009 1:14 PM
Hi,
We have one scenario that, one of cost posted to wbs on March 2006, it was settled to AUC, on April 2009 only. But as per our company policy whatever cost available in wbs, it has to be settled in subsequent month based on settlement rule.
My query is why the system was made settlement in April 2009 instead of April 2006. How to find out which parameter was not maintained to run settlement. Is there any log available .
Your immediate response in this regards will be highly appreciated.
With regards,
V.k
What is the process of settlement in your Orgn?
Is it settled manually or is it a batch job during each period end ? If its manual then somebidy might have missed it. If it was a batch job, on what criteria are the variants defined for batch job ? Chk the variants in CJ8V. How did settlement happen in Apr 2009?
Pls provide some input on above questions, to have some answers....
Sarang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For collective settlements, you have to define variants n then run a job in background or manaully by selecting variant. You define the group of WBS in variant which you would like to settle each period end. You might also set some Status limitaions for particular WBS to be picked up.
So my question was how were the Variants defined? Someone might have missed that WBS in Variant and hence it was not settled earlier. Pls chk you variants defined in CJ8V for your batch jobs.
Thanks
Sarang