Dear SAP PS Experts !

Can we split the Costs of the Activity say materials and external costs over the duration of the activity.

For the cost planning we have WBS wise can we have activity wise sothat say the duration of the activity is 3 months can we split the same into 3 months linearly.

Please provide your inputs !

Thanks!

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks!

Makal
Active Contributor
0 Kudos

As per virendra's suggestion,

you schedule your network. For cost planning use network costing.

Former Member
0 Kudos

I have run the network costing but how do I then split the Costs in the duration of tyhe network

regards,

A S

Former Member
0 Kudos

Use the distribution key as 1 in Activity planning.

virendra_pal
Active Contributor
0 Kudos

you will need to schedule network and then use the distribution profile (either on the internal activity or pon the work centre) to spread the activity costs over time