I would like to revise my earlier question.Ok,i deactivated availabilty control with CJBW..also in the extras the availabilty control is shown deactivated.However the moment i release the budget,it becomes activated and shows an error of excess budget.why is it not workin?Can U help?
Hi
In Budget profile in availability control tab waht activation type u maintained. If u maintained it as 1 and ticked on releases at time of CJ32 it will show the message. U maintain activation type as 0 i.e. for Cannot be activated in OPS9 then Thru CJEN reconstruct project info. Then try CJ32.