Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

VPK1121

Good morning Experts!

I am doing sales pricing for Project by DP82.

I find an error: No ordering party exists in project Cu2026..

Message no. VPK1121

I have two WBS elements with different partners in this project.

Does anybody know if it is possible to create a quotations based on separate WBS elements with different partners belonging to one Project?

When I enter partner in Project definition level I donu2019t have any problem for sales price calculation.

Former Member
Former Member replied

Hi,

Use DP81 for this you need to create a sales inquiry,enter DIP profile in sales b tab and assign the wbse in the account assignment tab.

Muzamil

0 View this answer in context