Release strategy

We want to configure the release strategy .

Our requirement is that once the PO is released and after releasing when user changes any thing like Price, quntity etc. PO should again go for release.

What is the Chgable indicator that should be used in release strategy.

Best Regards,



Hi all,

Thanks for replying.

I have kept the chgble indicator 6, but i observed that increaing the PO value is triggering the new release .

But lowering the PO value/quntity is not triggering the release.

I want if any thing ( Price / Qty) in the released PO is changed ( either decreased/increased ) system should again trigger the release strategy.