I am trying to enter a service order for a service material in our system and the warning I get is missing cost center but the cost center field in Acct Assignment at item level is not there; the profit center is there and blank. I was looking at a different sales org with same order type and material and at item level I see cost center field filled in and the profit center field blank. How is this being determined for the sales order with data for cost center? Where in IMG is this setup?
Hi
Maintain the profit centre in MM02 material master in the tab sales general/plant in the sub head
general plant parameters you will find the field profit centre you issue will be resolved
based on this profit centre system determines the cost centre
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Garqa,
Profit Center or Cost Centre is missing for the materials.
Maintained Profit Center for given sales area in Material Master.
Hope it will help.
Thanks,
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.