Where do check next cycle counting date?

0 Kudos

Using OMCO i have set cycle count indicators for plant 1100 as such

A - 4 times a year

B - 2 times a year

C - 1 time a year

D - 1 time a year

Using MICN for material 111 which has cycle count indicator A, I have created Physical Inventory Document on 14 May 2009,I have counted and cleared this. So as per my config the next one should be 14 August 2009 (3 months from now 4 times a year i.e. every 3 months).

My question is where can I see that this materials next cycle count is to be done on 14 August?

Is there any place in the material master or some other tcode?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

there is nothing in standard SAP that shows you the next counting date.

there is nothing in standard SAP that showns you which materials will be included in physical inventory counducted on date xx.xx.xxxx

Develope your own report.

Answers (1)

Answers (1)

Former Member

Hi,.

Check t.code MI23 it gives u the date of last count and it has got fields like current period and prev period.

Hope this helps u

Regards

AM.

0 Kudos

I checked ME23 it doesnt show anything about the next proposed cycle counting date.

Former Member
0 Kudos

Hi,

I don't think so u will get the exact date for the next count in any t.code.In MI23 u will get the last count date.Or else u can develop your own program by reading the last count date and the current ABC indiactor what will be the next month and year for the count.

Regards

AM