Where do check next cycle counting date?

Using OMCO i have set cycle count indicators for plant 1100 as such

A - 4 times a year

B - 2 times a year

C - 1 time a year

D - 1 time a year

Using MICN for material 111 which has cycle count indicator A, I have created Physical Inventory Document on 14 May 2009,I have counted and cleared this. So as per my config the next one should be 14 August 2009 (3 months from now 4 times a year i.e. every 3 months).

My question is where can I see that this materials next cycle count is to be done on 14 August?

Is there any place in the material master or some other tcode?



there is nothing in standard SAP that shows you the next counting date.

there is nothing in standard SAP that showns you which materials will be included in physical inventory counducted on date xx.xx.xxxx

Develope your own report.

0 View this answer in context