Hi,

Whem i created a sales order, the ATP is check and if the quantity is confirmed. But when the quantity is partial confirmation the saler order maintains an outstanding. How do I get the SAP makes a periodical verification of the difference?

Thks

Filipe B.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi

check them in

V_V2 rescheduling of sales orders

V_R2 rescheduling of sales order evaluate

regards

Former Member
0 Kudos

hello, friend.

you have the following options:

1. go to the sales order in change mode (VA02) and re-confirm schedule lines or repeat "check item availability"

2. do the same for several documents using the rescheduling functionality (V_V2)