on 05-14-2009 8:52 AM
Hi Experts,
I have a question about transportation.
I assigned a new partner type to a partner function, when I tried to save it, the system did not ask me to provide a TR number, instead the message popped up u2018Please process table entry transfer manuallyu2019. But the client wants to transport the change through TR.
Is there any method to include the change to TR?
Thanks,
Emily
Hi Emily,
Go to the place where you have assigned the partner type . Select that particular record which you want to transport and follow the menu path.
Table view -> Transport.
System gives a request number . Press enter. Then Click on the button on the application bar INCLUDE IN REQUEST and then click on the SAVE.
Now you can transport that request.
Regards,
Sai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.