Route and Loading Time

All Gurus:

I am trying to create a route for a specific shipping point (one plant) where the loading time is different for every route. I am looking at configuration for defining shipping point:

IMG > Enterprise Structure > Definition > Logistics Execution > Define, copy, delete, check shipping point. Under "Determine Times", there is "Determine load. times" and 4 options:

No loading time determination

A Route dependent

B Route independent (Route ' ')

C Default from shipping point

If select "C" and specify 11 days for "Loading Time with Days", the system will always have 11 days defaulting on the sales order schedule lines between the "Loading Date" and the "Goods Issue Date".

What I need is to have more flexibility as to the number of days on the Loading time. If I select A or B, can you please let me know what that would do and where I can configure it so that the system gives me more flexibility as to the number of Loading Days?

Thanks in advance,

Ta

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question