Process of PGI to Production order

Former Member
0 Kudos

Can any one please describe the porcess of googs issue to Productrion order/Network order(CN23)

with the transactions and mov types.Also the creation or tranfer orders and confirmations process.

Thanks for the help in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please let me know if you need any additional information.

Former Member
0 Kudos

Thanks for your reply,When you say TO is created .Is the TO created automatically? And Also can you please mention the process in T-codes like Co01 -


>Lt01---->Lt06 like this..plus the Mov types .Also you mentioned the last step the good is placed Mov type 103 can you please explain that a bit more.

Thanks in advance

Answers (1)

Answers (1)

Former Member
0 Kudos

ok when you say transfer order i assume you are using WM.Once the production order is released a TR is generated, with respect to the TR we create a TO to stage the materials to build the kit.The movemenmt type acting here is mvt 319.once the TO is created the source will be bins in the ware house and the destination will be a 9** interim staging area where we can either choose dynamic bins with the production order number or fixed bins. when physically the parts are moved to the staging area and after the kit is built the TO is confirmed and a 261 goods issue is done on teh production order.On activating auto GR in the production scheduling profile the kit will be automatically received into the bins using mvt type 103.Once the kit is received the production order is confirmed and technically complete.The basic config for this whole process can be understood by teh production scheudling profile, work center control cycle and production supplky area.

Regards

Kiran V Yarlagadda