on 05-13-2009 3:42 PM
Hi,
where we can see receipt date with reference to Schedule lines( not with reference to Items) in Schedule Agreement
Thanks in advance.
Best Regards,
Kapil.
Table EKET.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Table EKET is schedule line table and it consists only the Scheduled and statistical delivery dates, the Open and GR Qty but not the receipt date against the schedule lines. The receipt dates are stored in the EKBE (History per Purchasing Document) tables but this dates are stored against the Purchase doc item number but not the schedule line no.
System generally fills the scedule lines in the chronological orders based on the GR qty.
RJ
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.