creation of budget billing

Former Member
0 Kudos

Hi dudes,

Iam trying to create the budget billing plan.

in step 1,i went to EA61.

STEP 2: I eneterd the contract number.

step 3.i executed and error rises saying

" contract account so ans o needs to be changd for budget billing 01 or 02"

i have changed it then still the same error occurs.

kindly let m e know vat r the stpes to proceed to create a budget billing.

kr

raj

1 REPLY 1

rajesh_popat3
Active Participant
0 Kudos

Hi,

For creating the budget billing plan via EA61, please try choosing the budget billing procedure as 1 or 2 in CA.

You might be getting the message in EA61 as:

This is not possible, because the value in the BB procedure (budget billing procedure) field in contract account XXXXXX no longer represents a budget billing procedure (1 or 2). It is therefore not possible to create a budget billing plan. You can only create a payment plan (procedure 3) using Simulate Payment Schedule.

Please check if the corresponding budget billing procedure is configured correctly in SPRO.

path: SPRO -> SAP Utilities -> Invoicing -> Budget Billing Plan -> Basic Settings.

Regards,

Rajesh Popat