Hi all,

users have problem when they enter invoice for this material 500000005. Systems stops transaction MIRO and pop up this mesg.

I know that they must release the price first. However, it is already late to release as user already issued this material to production.

Now, if I deactivate this mesg in Customizing of the user-defined messages of logistics invoice verification (MIRO), is there any problem if I do it?

Next month, I'll activate this mesg again.

Thanks in advance,

Accepted Solutions (1)

Accepted Solutions (1)

former_member182098
Active Contributor

Hello,

Go to OBA5

Give application area M8

Message Number 394

Make warning message for online and batch entries.

Hope this resolves your issue.

Regards,

Ravi

Former Member
0 Kudos

Hi,

I still wonder that is there any problem if I change that mesg status?

BR

Former Member
0 Kudos

No problem, U can change the message.

rajeswari

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Update the plan price for that material 50000....5. Or you can change the message control to warning.