Defining the Business Process Structure

Former Member
0 Kudos

Dear All,

I am defining the Business Process Structure in SOLAR01.. by default we will get the following Structure

Project

Master Data

Organization Structure

Business Scenario

Business Process

Business Process Step

My Question here is , i want to add some node on parallel to to Business Scnario and Business process. as per my knowledge it is not Possible . But you guys did something on this please let me know.

Project

Master Data

Organization Structure

Business Scenario

non-SAP business scenario

Business Process

Business Process Step

non-SAP business process

Business Process Step

Could some expert suggest on this ?

Accepted Solutions (0)

Answers (1)

Answers (1)

prakhar_saxena
Active Contributor
0 Kudos

Dear Prakash,

In solution manager till EHP1 it is not possible to meet what is ur requirement but you can do the following as an alternative

Project

Master Data

Organization Structure

Business Scenario Std Selected from BPR e.g Service Desk

Business Process std

Business Process Step Std

Business Scenario Non Std Directly entered the name of scenario in Structure tab e.g any Zscenario

Business Process Non std ( you need to add here the process for zscenario)

Business Process Step Non Std ( you need to add here the process step for z*)

But if you very specific to go with 4 main nodes as you said then you need to modify the standard with ABAP Developement and there is no alternative.

Hope it clarifies.

Regards

Prakhar

Former Member
0 Kudos

But what you have explained can be maintained only under business scenario node, as follows

business scenario

-


non sap business scarnio name

but my question is there any way i can define as follows,

business scenario

-


sap business scenario names

non -sap business scenario

-


non sap business scenario names

i hope this is not possible. please confirm.

Yes, using ABAP program its possible, but i am exploring the standard availability.

prakhar_saxena
Active Contributor
0 Kudos

Dear Prakash,

whatever you see in solar01........... the 3 nodes are standard only .

Now if your req is to have 4 nodes then it is not possible to customize the same and only solution is to go for ABAP Development or modification.

I hope your doubt is clear now.

Regards

Prakhar