PS: Planned Progress and Actual Progress

Hi Guys,

I m working on PS Progress Analysis report. I want to calculate planned and actual progress of a particular project. I can't find the field or table name for that after SQL Trace. But, planned and actual progress is calculated in SAP standard report CNE5. Pls. Help me in this regards.


Muhammad Sohail


I guess you first run CNE1 for progress determination and then CNE5 for reporting....

I think the POC values can be checked via transaction CNE5 or CNSE5 (be sure to use the correct Progress Version) or directly on the database table COSR (value type 'P1' for planned POC and 'P2' for actual POC). The values in COSR are delta values!