on 05-13-2009 6:58 AM
Hi All
How to release the Projects collectively, is there any seperate transaction code for this.
Thanks
S.Murali
Hi,
There is no transaction for collective release of Project.
You will have to go for Development.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can write BDC by using CJ02 txn via SHDB recording. This will be easy for the development. As system status is havding dependancy on other objects and pass on nature, the mass change is not allowed for the same in any std. PS txn.
Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Murali,
There is no standard way to release project definitions collectively.
You can create your own report to do this. You can use BAPI_BUS2001_SET_STATUS in the report to release Project definitions.
Regards,
Anuradha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
According to me you can release project defn.individually.
In one project you can release multiple wbs elements at a time.
But multiple project defn.release is not available in standard sap ps.
sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.