on 05-13-2009 6:44 AM
Hai Guys,
I am posting this message after going through the forum thoroughly...
I am working on the Material determination scenario, where I have to substitute the material 100000 with 100001 ONLY if there is not enough qty available for 100000.
I have chosen 0004 as the reason for substitution.
There are enough stock for that article 100000, but still the system replaces with the substitute article 100001.
I tried with other option 0007 with the strategy B (General Article Determination with selection. without ATP), still I am unable to solve the issue.
Can somebody help me in this regard?
Regards,
Maheshwaran. I
Hi there,
After you maintain the condition records, i believe you also need to maintain the code in requirement routine in the procedure. In the routine put a code that only if material X is not available in SO, only then system should replace with Y.
Regards,
Sivanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.