Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

standard value key- labor cost


Standard value key in my work centre has two parameters: machine and labor.

My client says if a work centre is a lathe machine and one worker works and one supervisor works, their wages are to capture overall/individual cost labor cost.

sometimes one worker and one engineer , one supervisor and one senior labor works on one work centre(this work centre may be group of machines), in these cases how to capture labor cost individually . Do I need to increase the parameters in standard value key. but i can have only maximum 6 parameters. How about if I have more parametrs to be captured in the way I explained above.


Not what you were looking for? View more on this topic or Ask a question