Planned delivery time

Hi All,

If I maintian planned delivery time in vendor master, info record and material master then which planned delivery time sytem picks during MRP run? Can you please explain me with suitable example.Any doucement relevant to this very helpful to me..

Regards,

Alex

replied

You maintain the non-vendor-specific planned delivery time in the material master (view "MRP 2"). You enter a vendor-specific planned delivery time in the purchasing info record or in the outline agreement. It is used in the planning run, if the indicator "Scheduling info record/agreement" in Customizing is maintained as a plant parameter (OPPQ) or MRP group parameter in 'external procurement' and if, in the area of automatic source determination, an individual vendor can be assigned.

If you set this indicator, the system checks whether a planned delivery time is pentered in the purchasing info record or in the outline agreement. This planned delivery time is then used to calculate the delivery date and the release date.

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question