auto matic confirmation for milestone

Former Member
0 Kudos

Hi Experts,

can anybody tell me the standard t-code or program for confirming milestones rathe than putting the dates manually in the milestone which is attached to a WBS element.

Ashis

Accepted Solutions (1)

Accepted Solutions (1)

stheurkar
Active Contributor
0 Kudos

Hi,

Ind: Set milestone dates automatically:

With this indicator you specify that the actual dates from the confirmation are automatically transferred to the actual dates of the milestones.

Example:

An operation has milestones for a degree of processing of 50% or 75%. If you confirm a degree of processing of 60% then the actual date from the confirmation is transferred as the actual date for the first milestone.

Enter OPST transaction for Conformation Parameters.

In Default Values subscreen

Propose dates & Milestone automatic check boxes must be ticked.

Then see Mass Confiramtion subscreen

Execute Milestone Function check box must be ticked.

I think by doing this setting in spro you can trigger Milestone automatically.

Sandeep

Edited by: Sandeep Theurkar on May 12, 2009 12:24 PM

Former Member
0 Kudos

but here i m attaching mile stone to WBS elements not to activty.

Also sceduling is not being carried out for WBS.

In that case what to do ?

Ashis

Answers (1)

Answers (1)

Former Member
0 Kudos

.

Former Member
0 Kudos

manual entry is the only option & it has to be like that only.

if you have bigger number of milestones to be confirmed ,then go for program

Former Member
0 Kudos

manual entry is the only option,

If you have bigger number of milestones ,use CN53 for mass milestone overview for faster confirmation

otherewise u can go for program