Hi PP experts,
I want to split my production order qty. on two different work center. Can u tell me how it possible.
Thanks in advanace
Jayesh
SAP PP
Dear Jayesh,
Check out this,
You can create 2 production versions ,the first one with the first production line(work center) and the
second one for the second work center.
Then while assgining the Planned independent requirements itself you can assign the relevent
production version in MD61 or else oen more thing using quota arrangement you can assign some %
and also the priority among the 2 prod.versions.
Quota arrangement details has to be given in MEQ1.
So this will be helping you automatically at the time of MRP run itself and you can convert the planned
orders into production orders.
Check and rever back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.