Hi all

Could you please assist. I want to make sure that my Landscape is setup correctly for the "graphical" display to work in the Solution directory. i have used SMSY to create everything. I have a DEV, QAS and PRD on ECC6. When I run SOLUTION_MANAGER, I do not see the systems to be monitored.

What can I do to "fix' this?

Jaco

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi, I found the problem. "BACK" RFC not working and Logical Componant not assigned. Jaco

Former Member
0 Kudos

Hi,

Have a look into the below link

[http://help.sap.com/saphelp_smehp1/helpdata/en/b3/64c33af662c514e10000000a114084/frameset.htm|http://help.sap.com/saphelp_smehp1/helpdata/en/b3/64c33af662c514e10000000a114084/frameset.htm]

Former Member
0 Kudos

Hi Mohammed

My problem is that I have done it, but when I click on it, it does not display the 3 systems which are setup.

Jaco

raguraman_c
Active Contributor
0 Kudos

Hi,

DSWP --> Select Solution --> Solution Landscape --> Solution Landscape Maintenance, Maintain Logical Components there.

Hope this solves your problem.

Feel free to revert back.

-=-Ragu

Former Member
0 Kudos

Hi Ragu

I think my Solution is not setup coreectly. How do I populate the data for the Solution to show my 3 systems?

Jaco

raguraman_c
Active Contributor
0 Kudos

Hi,

Did you create logical component using SMSY.

Feel free to revert back.