I am using strategy 10. I am giving the monthly plan for consecutive 12 months from now on. If I run MRP, system is planning and throwing the requirements for all the 12 months.

Is it possible to have only first 3 months requirement planned by system and keep rest of the requirements are unplanned / hidden?

Rex

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Pls check how many days are defined as planning horizon in Trx OMDX.

Is it more than 100 days?

Thanks & Regards

Kundan Kumar

Former Member
0 Kudos

Hi,

It is only 100 days. Even then it is planning for all the moths.

Rex

Former Member
0 Kudos

Hi,

Pls chk the same thing if you are maintaing a mrp group for material in the same Trx.

Thanks & Regards

Kundan Kumar

former_member335796
Active Contributor
0 Kudos

Hi,

Planning horizon is Used when you use the Processing Key - NETPL in MD02.

If the processing key is NETCH, the Planning horizon will not have any impact on the Planning..

So, change your Processing Key to NETPL and Planing Mode - 3 in MD02/MD01..

Regards,

Siva

Former Member
0 Kudos

Hi,

While running MRP - MD02, Pls select Processing key NETPL under MRP control parameters.

Hope this will work for you.

Thanks & Regards

Kundan Kumar

Former Member
0 Kudos

Hi,

I have checked. There was nothing against the MRP Group(0031) I have assigned in OMDX. I have provide 100 against that. Even after that it is planning for all months.

Rex

Former Member
0 Kudos

Hi,

That is a MPS item. Will it not effect for the MPS run? Will it work only for MRP?

Rex

Former Member
0 Kudos

Hi,

You can Run MPS With processing key NETPL.

Thanks & Regards

Kundan Kumar

Former Member
0 Kudos

Thanks a lot Kumar. Its working with processing key NETPL.

Rex

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

As suggested system is giving the result as per the question raised .

My requirement is just opposite of the above question.

i.e: Is it possible to have first 3 months planned order for header material and 12 months pur req proposal for the ROH material (bought outs which is imported)?

CLS

Former Member
0 Kudos

Hi,

As suggested system is giving the result as per the question raised .

My requirement is just opposite of the above question.

i.e: Is it possible to have first 3 months planned order for header material and 12 months pur req proposal for the ROH material (bought outs which is imported)?

CLS